Objectives

* Urban infrastructure and service improvement.
* Improving connectivity.
* Quality enhancement of natural and cultural attractions.
* Greater participation by local communities.
* Capacity development, community participation and project management.

Development of Tourism Infrastructure in Kartikeya Swami Circuit - Durgadhar and Tungeshwar Temple

Main Temple at Durgadhar

Durgadhar & Tungeshwar - September-18

View Photos
Wood work at Main Temple -Durgadhar

Durgadhar & Tungehswar Temple 23.08.18

View Photos
Durgadhar Toilet

Durgadhar and Tungeshwar (03.05.18)

View Photos
Railing work at back side of guest house -Tungeshwar

Durgadhar and Tungeshwar

View Photos
Small toilet near parking -Durgadhar

Durgadhar and Tungeshwar ( 20.01.18)

View Photos
Unistone cladding for toilet block at Tungeshwar

Durgadhar and Tungeshwar (06.12.17)

View Photos
Main temple at Durgadhar

Durgadhar and Tungeshwar (15.10.17)

View Photos
Stone Masonary work at Guest House -Durgadhar

Durgadhar and Tungeshwar (17-08-17)

View Photos
column cast at Dharamshala -Tungeshwar

Tungeshwar Temple-25.11.2016

View Photos
Environment Monitoring test (Air,Water and Noise) -Durgadhar and Tungeshwar

Durgadhar 28-1-17

View Photos
Retaing wall and approach road from main road t temple -Durgadhar Project

Durgadhar-25.11.2016

View Photos
reinforcement work for RCC slabTugeshwar Guest House -Tungeshwar

Tungeshwar Temple- December-16

View Photos
Construction of Retainig wall at main temple -Durgadhar Project

Durgadhar-December-16

View Photos
Erection of column at existing for renovation at Durgadhar Temple

Durgadhar Temple

View Photos
volunteers of school students at Durgadhar temple for plantation work

Durgadhar & Tungeshwar

View Photos
News & Updates
  • ADB mission visiting IDIPT from August 27 to August 28, 2018.
  • 13th SLEC Meeting will be conducted on 05 July, 2018 at 05.00 pm under the Chairmanship of the Chief Secretary, Government of Uttarakhand at his Conference Hall.
  • Review Meeting held on  September 04th 2017 at UTDB Conference Hall. The Secretary & Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from May 23, 2017 till May 26, 2017. ADB Review meeting is going to be held on May 25,2017 at IDIPT conference hall.
  • UTTARAKHAND HIMMLAYAN MTB CHALLENGE  (3rd  Edition) of  8th - 16th April 2017 for participation ditails please visit website : www mtbuttarakhand.co.in
  • ADB mission visiting IDIPT from November 28, 2016 till December 02, 2016. ADB Review meeting is going to be held on December 01,2016 at IDIPT conference hall.
  • This is to inform you that Asan Conservation Resort,  Dehradun constructed under ADB Assistant Project is being inaugurated on 06 Aug 2016 by the Hon,ble tourism Minister, Govt of Uttarakhand
  • Review Meeting held on May 5 & 6 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • Review Meeting held on March 17 & 18 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from February 22 to February 25, 2016.
  • Work shop on environment and social safeguards 20th February 2016 IDIPT (UTDB)
  • Review Meeting held on February 9,10 & 11 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • Review Meeting held on January 23, 2018 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • ADB mission visiting IDIPT from March 27 to March 29, 2018.