Objectives

* Urban infrastructure and service improvement.
* Improving connectivity.
* Quality enhancement of natural and cultural attractions.
* Greater participation by local communities.
* Capacity development, community participation and project management.

Development of Adventure Tourist Centre in Uttarakhand - Lot 2 (Bageshwar) P-1

Kapkot (Bageshwar)-24.03.18

Kapkot (Bageshwar)-24.03.18

Layed kota stone at staircase Kapkot -Bageshwar

Layed kota stone at staircase Kapkot -Bageshwar

Uploaded on 05-May-2018
View Photo
Interpretation and caretaker building Kapkot -Bageshwar

Interpretation and caretaker building Kapkot -Bageshwar

Uploaded on 05-May-2018
View Photo
Current status of Interpretation building -Kapkot (Bageshwar)

Current status of Interpretation building -Kapkot (Bageshwar)

Uploaded on 25-Apr-2018
View Photo
Premier work at railing work is in progress-Kapkot (Bageshwar)

Premier work at railing work is in progress-Kapkot (Bageshwar)

Uploaded on 24-Apr-2018
View Photo
Internal putty work at Interpretation centre -Kapkot (Bageshwar)

Internal putty work at Interpretation centre -Kapkot (Bageshwar)

Uploaded on 24-Apr-2018
View Photo
Current status of Interpretation and manager and caretaker room -Kapkot (Bageshwar)

Current status of Interpretation and manager and caretaker room -Kapkot (Bageshwar)

Uploaded on 24-Apr-2018
View Photo
External wall surface cleaning and putty filling under progress-Kapkot Bageshwar

External wall surface cleaning and putty filling under progress-Kapkot Bageshwar

Uploaded on 20-Apr-2018
View Photo
External wall surface cleaning and putty filling under progress-Kapkot Bageshwar

External wall surface cleaning and putty filling under progress-Kapkot Bageshwar

Uploaded on 20-Apr-2018
View Photo
Interpretation and caretaker -Kapkot (Bageshwar)

Interpretation and caretaker -Kapkot (Bageshwar)

Uploaded on 13-Apr-2018
View Photo
Laying of Kota stone work is in progress -Kapkot

Laying of Kota stone work is in progress -Kapkot

Uploaded on 13-Apr-2018
View Photo
Electrical conduit fixing-Kapkot (Bageshwar)

Electrical conduit fixing-Kapkot (Bageshwar)

Uploaded on 05-Apr-2018
View Photo
Fixing of PPGI sheet at Interpretation center -Kapkot (Bageshwar)

Fixing of PPGI sheet at Interpretation center -Kapkot (Bageshwar)

Uploaded on 05-Apr-2018
View Photo
front elevation of the Building -Kapkot (Bageshwar)

front elevation of the Building -Kapkot (Bageshwar)

Uploaded on 05-Apr-2018
View Photo
Brick work and D & W frame work is in progress at first floor -Kapkot (Bageshwar)

Brick work and D & W frame work is in progress at first floor -Kapkot (Bageshwar)

Uploaded on 04-Apr-2018
View Photo
Brick work at ground floor including fixing of window and door frame at ground floor -Kapkot Bageshw

Brick work at ground floor including fixing of window and door frame at ground floor -Kapkot Bageshw

Uploaded on 24-Mar-2018
View Photo
Truss work is in progress-Kapkot Bageshwar

Truss work is in progress-Kapkot Bageshwar

Uploaded on 24-Mar-2018
View Photo
News & Updates
  • UTTARAKHAND HIMMLAYAN MTB CHALLENGE  (4th  Edition) of  18th - 26th April 2019 for participation ditails please visit CFI website- www.cyclingfederationodindia.org
  • ADB mission visiting IDIPT from  19  March, 2019.
  • ADB mission visiting IDIPT from August 27 to August 28, 2018.
  • 13th SLEC Meeting will be conducted on 05 July, 2018 at 05.00 pm under the Chairmanship of the Chief Secretary, Government of Uttarakhand at his Conference Hall.
  • Review Meeting held on  September 04th 2017 at UTDB Conference Hall. The Secretary & Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from May 23, 2017 till May 26, 2017. ADB Review meeting is going to be held on May 25,2017 at IDIPT conference hall.
  • UTTARAKHAND HIMMLAYAN MTB CHALLENGE  (3rd  Edition) of  8th - 16th April 2017 for participation ditails please visit website : www mtbuttarakhand.co.in
  • This is to inform you that Asan Conservation Resort,  Dehradun constructed under ADB Assistant Project is being inaugurated on 06 Aug 2016 by the Hon,ble tourism Minister, Govt of Uttarakhand
  • Review Meeting held on January 23, 2018 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • ADB mission visiting IDIPT from March 27 to March 29, 2018.