Sub-Projects (Tranche - II & Tranche - III)

Package No.
PCSS
Status / Contract Type
Contractor Name SLEC Approved DPR Cost (INR Crore) Contract Amount
(US $ Million)
($1=65.55 INR)
ADB Financing
(US $ Million)
($1=65.55 INR)
Agreement Date
UK/IDIPT/BHT/03/Lot 1
0013
Completed / Works
M/s Soar Valley Construction & G.S. Matiyani & Sons
Krishna puri, Near Bus Station, Pithoragarh, Uttarakhand, India

0.89

0.14

(INR 8.88 Million)
(INR 0.89 Crore)
With Variation
0.13
(INR 8.22 Million)
(INR 0.82 Crore)
0.08
59% of Award Value
03-06-2014
Contract Start Date Contract Period Completion Date
(As per contract start date)
Sub-Project Valley
01-07-2014 12 Months
Ext. 25.31(M)
02-06-2015
02-08-2017
30-06-2015
31-08-2017
Soar Valley
Contract start after 14 days from NTP. (i.e. 23-06-2014) Only 7 days delay due to unforseen circumstances.
Sub-Project Output
  • Improved connectivity
Overall Physical Progress(%) as on December 2017 & Financial Progress (%) till date
Physical Progress (%) Financial Progress (%) Disbursed
(INR Million)
Remarks
100.00 92.91 7.63 Work has been completed
Sub-Project Main Components / Scope of work View Photo Gallery
Latest Photos
Viewing shelters (3) Viewing shelters (3) Viewing shelters (2) Viewing shelters (2) Viewing shelters Viewing shelters
Public Consultation / Disclosure / Orientation Meeting Total Employment (Skilled / Unskilled) Labor
No. of Community member involved
Male Female Total Male Female Total
Pollution Status
AIR
Parameter Base Data Present Data
PM10 61 65.10
SO2 06 7.35
NO2 24 17.40
CO 0.14 0.40
Base Data: 06-11-2013
Present Data: 06-11-2013
Base Data Report Present Data Report
WATER
Parameter Base Data Present Data
Colour - <5
Turbidity - BDL
pH - 7.30
Total Hardness - 246.0
TDS - 182.0
MPN - <2/100
Faecal Coliform - Absent
Base Data: 06-11-2013
Present Data: 15-03-2016
Base Data Report Present Data Report
NOISE
Parameter Base Data Present Data
Average 44.5 dB(A) 43.2 dB(A)
Maximum 46.6 dB(A) 50.6 dB(A)
Minimum 41.5 dB(A) 38.4 dB(A)
Leq. dB(A) 43.5 dB(A) 55.0 dB(A)
Base Data: 06-11-2013
Present Data: 15-03-2016
Base Data Report Present Data Report
News & Updates
  • ADB mission visiting IDIPT from August 27 to August 28, 2018.
  • 13th SLEC Meeting will be conducted on 05 July, 2018 at 05.00 pm under the Chairmanship of the Chief Secretary, Government of Uttarakhand at his Conference Hall.
  • Review Meeting held on  September 04th 2017 at UTDB Conference Hall. The Secretary & Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from May 23, 2017 till May 26, 2017. ADB Review meeting is going to be held on May 25,2017 at IDIPT conference hall.
  • UTTARAKHAND HIMMLAYAN MTB CHALLENGE  (3rd  Edition) of  8th - 16th April 2017 for participation ditails please visit website : www mtbuttarakhand.co.in
  • ADB mission visiting IDIPT from November 28, 2016 till December 02, 2016. ADB Review meeting is going to be held on December 01,2016 at IDIPT conference hall.
  • This is to inform you that Asan Conservation Resort,  Dehradun constructed under ADB Assistant Project is being inaugurated on 06 Aug 2016 by the Hon,ble tourism Minister, Govt of Uttarakhand
  • Review Meeting held on May 5 & 6 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • Review Meeting held on March 17 & 18 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from February 22 to February 25, 2016.
  • Work shop on environment and social safeguards 20th February 2016 IDIPT (UTDB)
  • Review Meeting held on February 9,10 & 11 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • Review Meeting held on January 23, 2018 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • ADB mission visiting IDIPT from March 27 to March 29, 2018.