Sub-Projects (Tranche - II & Tranche - III)

Package No.
PCSS
Status / Contract Type
Contractor Name SLEC Approved DPR Cost (INR Crore) Contract Amount
(US $ Million)
($1=65.55 INR)
ADB Financing
(US $ Million)
($1=65.55 INR)
Agreement Date
UK/IDIPT-III/DDN/03
0028
Awarded / Works
M/s Navya associates, Dehradun in JV with M/s Agarwal Brothers
Dehradun Uttarkhand

15.26

2.33

(INR 152.60 Million)
(INR 15.26 Crore)
With Variation
2.27
(INR 148.99 Million)
(INR 14.90 Crore)
1.51
65% of Award Value
02-08-2016
Contract Start Date Contract Period Completion Date
(As per contract start date)
Sub-Project Valley
02-08-2016 24 Months 01-08-2018 01-08-2018 Mandakini,Alaknanda & Bhagirathi Valley
Sub-Project Output
  • Improved connectivity
  • Enhanced quality of natural and cultural attractions
  • Urban infrastructure and services at tourist destinations and attractions
Overall Physical Progress(%) as on October 2018 & Financial Progress (%) till date
Physical Progress (%) Financial Progress (%) Disbursed
(INR Million)
Remarks
40.00 34.16 50.89 Tungnath Temple:-
Gabion wall:- Gabion wall work is in progress and drain work completed is in progress. Akash kund work is in progress , rain shelter work is in progress
Harshil:-Camping site and kitchen block wall work completed , Stone claddding work at entrance gate work is in progress
Mukhba : Wooden clading at entrance gate work is in progress , Bhogshala flooring work is in progress.
Kaviltha:- flooring work at ground floor and fixing of door & window work is in progres at Guest house
Phalasi:- Railing and sitting bench work completed .
Niti:- Entrance gate RCC work completed, Slab casting work of ground floor completed at Community centre , Big toilet RCC work and slan work completed , sanitary and flooring work is in progress , pathway work is in progress, foundation work at glass house work is in progress.
Bora:- Plaster work & RCC roof projection work complted at panchayat bhawan ,pathway work is in progress
Mori:-Interpretation and caretaker room work completed
1st RA Bill:- Rs. 47,63,713.46
2nd RA Bill:-Rs. 46,50,084.65 with a Gross amount of Rs.94,13,798.11
3rd RA Bill :- Rs. 50,71,353.12 with a gross amount of Rs. 1,44,84,994.87
4th Ra bill Rs.39,51,662.82:- with a gross amount of Rs.1,84,36,814.05
5th RA Bill :Rs.4385891.80 with a gross amount Rs.22764194.00
6th RA Bill:- Rs. 1514529.70 with a gross amount of Rs.24278723.70
7th Ra Bill:-16,43,254.04 witt a gross amount of Rs. 2,59,21,792.48
8th RA Bill:-1,8753,500.88 with a gross amount of Rs.4,46,75,293.34
9th RA Bill:- 1,08,06,099.33 with a gross amount of Rs. 5,54,81,392.69
Sub-Project Main Components / Scope of work View Photo Gallery
    Latest Photos
    Existing shelter work-Tungnath Temple under Rural Tourism project Existing shelter work-Tungnath Temple unde... Gabion wall work is in progress -Tungnath Temple under Rural Tourism project Gabion wall work is in progress -Tungnath ... drain work is in progress -Tungnath temple under rural tourism drain work is in progress -Tungnath temple...
    Public Consultation / Disclosure / Orientation Meeting Total Employment (Skilled / Unskilled) Labor
    No. of Community member involved
    Male Female Total Male Female Total
    300 300
    Pollution Status
    AIR
    Parameter Base Data Present Data
    PM10 56.54
    SO2 7.10
    NO2 17.25
    CO 0.28
    Base Data: 10-10-2016
    Base Data Report
    WATER
    Parameter Base Data Present Data
    Colour <5
    Turbidity BDL
    pH 7.56
    Total Hardness 212.20
    TDS 280.50
    MPN Not Detected
    Faecal Coliform Absent
    Base Data: 10-10-2016
    Base Data Report
    NOISE
    Parameter Base Data Present Data
    Average 45.8
    Maximum 52.4
    Minimum 39.2
    Leq. dB(A) 55.0
    Base Data: 10-10-2016
    Base Data Report
    News & Updates
    • ADB mission visiting IDIPT from August 27 to August 28, 2018.
    • 13th SLEC Meeting will be conducted on 05 July, 2018 at 05.00 pm under the Chairmanship of the Chief Secretary, Government of Uttarakhand at his Conference Hall.
    • Review Meeting held on  September 04th 2017 at UTDB Conference Hall. The Secretary & Program Director, IDIPT chaired the meeting
    • ADB mission visiting IDIPT from May 23, 2017 till May 26, 2017. ADB Review meeting is going to be held on May 25,2017 at IDIPT conference hall.
    • UTTARAKHAND HIMMLAYAN MTB CHALLENGE  (3rd  Edition) of  8th - 16th April 2017 for participation ditails please visit website : www mtbuttarakhand.co.in
    • ADB mission visiting IDIPT from November 28, 2016 till December 02, 2016. ADB Review meeting is going to be held on December 01,2016 at IDIPT conference hall.
    • This is to inform you that Asan Conservation Resort,  Dehradun constructed under ADB Assistant Project is being inaugurated on 06 Aug 2016 by the Hon,ble tourism Minister, Govt of Uttarakhand
    • Review Meeting held on May 5 & 6 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
    • Review Meeting held on March 17 & 18 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
    • ADB mission visiting IDIPT from February 22 to February 25, 2016.
    • Work shop on environment and social safeguards 20th February 2016 IDIPT (UTDB)
    • Review Meeting held on February 9,10 & 11 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
    • Review Meeting held on January 23, 2018 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
    • ADB mission visiting IDIPT from March 27 to March 29, 2018.

    Other Links