Sub-Projects (Tranche - II & Tranche - III)

Package No.
PCSS
Status / Contract Type
Contractor Name SLEC Approved DPR Cost (INR Crore) Contract Amount
(US $ Million)
($1=63.00 INR)
ADB Financing
(US $ Million)
($1=63.00 INR)
Agreement Date
UK/IDIPT/KOT/01
0018
Awarded / Works
M/s Dagmo Riba
Ground Floor, A-3, 49-50, Sector-11, Rohini Delhi - 110085

11.84

1.75

(INR 110.08 Million)
(INR 11.01 Crore)
With Variation
1.91
(INR 120.07 Million)
(INR 12.01 Crore)
1.03
59% of Award Value
09-07-2014
Contract Start Date Contract Period Completion Date
(As per contract start date)
Sub-Project Valley
09-07-2014 17 Months
Ext. 18.84(M)
08-12-2015
31-08-2017
08-12-2015
31-08-2017
Tarai Valley
Sub-Project Output
  • Urban infrastructure and services at tourist destinations and attractions
Overall Physical Progress(%) as on January 2018 & Financial Progress (%) till date
Physical Progress (%) Financial Progress (%) Disbursed
(INR Million)
Remarks
97.00 76.39 99.45 1. Cottages for the tourists – 8 Nos. - Completed
2. Convention Centre cum Restaurant – Completed
3. Interpretation Centre - Completed
4. Existing Guard Room & Temple – Completed
5. Staff Quarters – Completed
6. Rehabilitation Staff Quarter- Completed
- Final Painting is yet to be completed
- Bathroom Fittings- in progress
7. Gas Godown(converted into General Staff Quarter)- Finishing work is in progress
8. Repairing of Boundary wall – 95% completed.(Colouring work is in progress),
9. OHR – completed.
10. Entrance Plaza-01-t completed.
11. Landscaping and Pathway-work in progress.
12. Car Parking- work in progress,Paver Block work is in progress.
13. Generator Shed: completed
14. Musical Fountain(Civil) - completed.
15.Septic Tank-Completed.
16.Climbing Wall- Completed
17. New Construction of Gas Godown as per approved Drawing of GMVN:completed.Finishing work completed.
18. Entrance Plaza-2: almost in final stage
19.Plumbing Works: It is under progress.
20. Drain - Almost completed
21.Furniture - Procurement completed,Installation to be completed before hand over
Sub-Project Main Components / Scope of work View Photo Gallery
Latest Photos
Current Status of Shifting of Existing Gas Godown Current Status of Shifting of Existing Gas... Current Status of Rehabilitation Quarter for existing staff of gas godown Current Status of Rehabilitation Quarter f... Current Status of Landscaping Current Status of Landscaping
Public Consultation / Disclosure / Orientation Meeting Total Employment (Skilled / Unskilled) Labor
No. of Community member involved
Male Female Total Male Female Total
Pollution Status
AIR
Parameter Base Data Present Data
PM10 76.3
SO2 14.5
NO2 11.7
CO N.D.

Present Data: 23-11-2016 Present Data Report
WATER
Parameter Base Data Present Data
Colour <5
Turbidity Nil
pH 7.3
Total Hardness 166
TDS 376
MPN Not Detected
Faecal Coliform Not Detected

Present Data: 23-11-2016 Present Data Report
NOISE
Parameter Base Data Present Data
Average 59.25
Maximum 60.6
Minimum 57.9
Leq. dB(A) 59

Present Data: 23-11-2016 Present Data Report
News & Updates
  • Review Meeting held on  September 04th 2017 at UTDB Conference Hall. The Secretary & Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from May 23, 2017 till May 26, 2017. ADB Review meeting is going to be held on May 25,2017 at IDIPT conference hall.
  • UTTARAKHAND HIMMLAYAN MTB CHALLENGE  (3rd  Edition) of  8th - 16th April 2017 for participation ditails please visit website : www mtbuttarakhand.co.in
  • ADB mission visiting IDIPT from November 28, 2016 till December 02, 2016. ADB Review meeting is going to be held on December 01,2016 at IDIPT conference hall.
  • This is to inform you that Asan Conservation Resort,  Dehradun constructed under ADB Assistant Project is being inaugurated on 06 Aug 2016 by the Hon,ble tourism Minister, Govt of Uttarakhand
  • Review Meeting held on May 5 & 6 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • Review Meeting held on March 17 & 18 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from February 22 to February 25, 2016.
  • Work shop on environment and social safeguards 20th February 2016 IDIPT (UTDB)
  • Review Meeting held on February 9,10 & 11 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • ADB & DEA has approved the Tranche - III and loan signing is fixed on September 28, 2015 in GoI, MoF, New Delhi.

  • ADB mission visiting IDIPT from September 21 to September 30, 2015.

    The objective is to observe the performance of ongoing sub-projects.

  • CTS Review Meeting held on September 14, 2015 at UTDB Conference Hall. Addl. Program Director, IDIPT chaired the meeting.

    The objective of the meeting was to discuss progress reports, identify new tourist destinations etc.

  • Review Meeting held on August 10, 2015 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.

    The objective of the meeting was to discuss the physical & financial progress of ongoing sub-projects of Tranche - II

Other Links