Sub-Projects (Tranche - II & Tranche - III)

Package No.
PCSS
Status / Contract Type
Contractor Name SLEC Approved DPR Cost (INR Crore) Contract Amount
(US $ Million)
($1=63.00 INR)
ADB Financing
(US $ Million)
($1=63.00 INR)
Agreement Date
UK/IDIPT-III/KOT/02
0014
Awarded / Works
M/s Mangalam Engineers & Construction Company in JV with Sunil Garg & Company
33 Kesarganj Mandi, Meerut, U.P

11.65

1.62

(INR 101.77 Million)
(INR 10.18 Crore)
With Variation
1.99
(INR 125.41 Million)
(INR 12.54 Crore)
1.05
65% of Award Value
22-08-2015
Contract Start Date Contract Period Completion Date
(As per contract start date)
Sub-Project Valley
22-08-2015 24 Months 21-08-2017 21-08-2017 Bhagirathi Valley
14 Days after date of NTP issued (i.e. 09-09-2015)
Sub-Project Output
  • Urban infrastructure and services at tourist destinations and attractions
Overall Physical Progress(%) as on September 2017 & Financial Progress (%) till date
Physical Progress (%) Financial Progress (%) Disbursed
(INR Million)
Remarks
62.00 41.10 47.86 1. Rest Shelter (including toilet complex): All Brick Work for superstructure is completed. RCC Slab casting completed , PlastringIn Side Completed, Outer Side Completed ,Plumbing Work 30% Completed,Kota Stone Flloring Work Completed, Toilet Wall tile Work 80% Completed and ,Flooring work 80% completed ,Painting Work is in progress.
1 (a) compound wall Brick work 90% Completed , Plaster Work 90 % completed and Railling Work 90% completed , painting Work is in progress. 2.Pathway in fair ground WBM 90% completed,C.C work 90 % Completed.Paber block work is in progress
3. Drain and plantaition at fair ground Brick work 95% completed Plaster Work 80% Completed.
4.Rest shed 5 nos Three Rest Shed RCC work completed,painting work is in progress
5 (a). car parking work WBM completed,C.C work Completed, karb stone work completed,paber block work completed 5 (b). Fair Ground - Main Stair (Frount), Long Stair, Gate Stair, Drain Near Tea Stall, Cross Drain Upper Side, Yard Stair Upper Side, Toe Wall ,Stone Masonary work in Progress (90%).
5 (c).Renovation fair ground in progress(70%).
6. Development of Jheel: Silt clearing completed,Silt Clearance completed, Pitching work is completed,water tank,Kiyosk and Spilway in Progress .and Pathway Work is in progress
7.RCC Slab Casting of Pujari Cottage has been completed,Renovation work of village temple at Mukhem is in progress(80%),Flooring work is in progress.and painting work is in progress
8. Pathway for Mukhem Village completed.
9.G.I. Main Line from Chalagarh Source to Fair Groundcompleted,talbala sorce to tank completed ,tank to village temple and filter chamber to lake side tank in progress.filter chamber and collaction chamber in progress(90%).
10.Septic tank 30 user completed.
11. Underground Water Reservoir is complete.
Sub-Project Main Components / Scope of work View Photo Gallery
Latest Photos
Current Status of Rest Shelter Current Status of Rest Shelter Current Status of Rest Shelter Current Status of Rest Shelter Current Status of Pathway at Fair Ground Current Status of Pathway at Fair Ground
Public Consultation / Disclosure / Orientation Meeting Total Employment (Skilled / Unskilled) Labor
No. of Community member involved
Male Female Total Male Female Total
44 44 44 44
Pollution Status
AIR
Parameter Base Data Present Data
PM10 75.7
SO2 14.5
NO2 11.6
CO N.D.

Present Data: 01-02-2016 Present Data Report
WATER
Parameter Base Data Present Data
Colour <5
Turbidity Nil
pH 7.3
Total Hardness 175
TDS 378
MPN -
Faecal Coliform -

Present Data: 01-02-2016 Present Data Report
NOISE
Parameter Base Data Present Data
Average 57.25
Maximum 58.4
Minimum 56.1
Leq. dB(A) 57.0

Present Data: 01-02-2016 Present Data Report
News & Updates
  • Review Meeting held on  September 04th 2017 at UTDB Conference Hall. The Secretary & Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from May 23, 2017 till May 26, 2017. ADB Review meeting is going to be held on May 25,2017 at IDIPT conference hall.
  • UTTARAKHAND HIMMLAYAN MTB CHALLENGE  (3rd  Edition) of  8th - 16th April 2017 for participation ditails please visit website : www mtbuttarakhand.co.in
  • ADB mission visiting IDIPT from November 28, 2016 till December 02, 2016. ADB Review meeting is going to be held on December 01,2016 at IDIPT conference hall.
  • This is to inform you that Asan Conservation Resort,  Dehradun constructed under ADB Assistant Project is being inaugurated on 06 Aug 2016 by the Hon,ble tourism Minister, Govt of Uttarakhand
  • Review Meeting held on May 5 & 6 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • Review Meeting held on March 17 & 18 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from February 22 to February 25, 2016.
  • Work shop on environment and social safeguards 20th February 2016 IDIPT (UTDB)
  • Review Meeting held on February 9,10 & 11 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • ADB & DEA has approved the Tranche - III and loan signing is fixed on September 28, 2015 in GoI, MoF, New Delhi.

  • ADB mission visiting IDIPT from September 21 to September 30, 2015.

    The objective is to observe the performance of ongoing sub-projects.

  • CTS Review Meeting held on September 14, 2015 at UTDB Conference Hall. Addl. Program Director, IDIPT chaired the meeting.

    The objective of the meeting was to discuss progress reports, identify new tourist destinations etc.

  • Review Meeting held on August 10, 2015 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.

    The objective of the meeting was to discuss the physical & financial progress of ongoing sub-projects of Tranche - II