Sub-Projects (Tranche - II & Tranche - III)

Package No.
PCSS
Status / Contract Type
Contractor Name SLEC Approved DPR Cost (INR Crore) Contract Amount
(US $ Million)
($1=65.55 INR)
ADB Financing
(US $ Million)
($1=65.55 INR)
Agreement Date
UK/IDIPT-III/KOT/01
0004
Awarded / Works
M/s S.S. Infratech JV
Tikola Nagar, Roorkee, Haridwar - 247670

25.07

3.41

(INR 223.83 Million)
(INR 22.38 Crore)
With Variation
3.80
(INR 249.10 Million)
(INR 24.91 Crore)
2.22
65% of Award Value
22-07-2015
Contract Start Date Contract Period Completion Date
(As per contract start date)
Sub-Project Valley
22-07-2015 24 Months 21-07-2017 21-07-2017 Ganga Valley
Sub-Project Output
  • Improved connectivity
Overall Physical Progress(%) as on July 2018 & Financial Progress (%) till date
Physical Progress (%) Financial Progress (%) Disbursed
(INR Million)
Remarks
62.50 34.14 85.03 Toilet Complex : 1. RCC work is done. 2. Brick work is completed. 3. Plaster Work is done. Guard Wall: 1. Brick Work is complete. 2. Plaster work and PCC over Brick work is under progress. 3. Tile work in guard wall is Complete. Integrated Complex: 1. RCC work is complete. 2. RCC of Tank is in progress 3. Plumbing work and electrical fitting are under progress. 4. Tile work at Toilet Complex is in Complete. 5. Boundary Work is in progress. 6. Kota stone flooring done. Pathway & Footpath at Sonali Park : 1. Road work is completed for 1 km. 2. Footpath work is in progress. 3. Paver Block work is in progress. Landscaping : 1. Tree Protecting structure is under progress. 2. Plantation is under process. 3. Plantation bed is under progress. Seating Arrangement : 1. Steating arrangement work is under progress. Rest Shed : 1. 5 numbers are under progress. one number of Slab casting is done. 2.Plaster work is in progress 3. Footing is under progress. Pipe Laying Work : 1. Trenching is in progress, Earth Filling :1. Earth filling along NH side is in progress OHR : 1. OHR for one number is done. 2. Cat ladder and pipe work is in progress. Gate of 9 nos: 1. Construction of gate for 3 no is in progress. Water Drinking Point : 1. 9 nos water point are in progress. 2. Plaster work is in progress. Railing At NH side : 1. B/w footing is in progress 2. Welding of Railing is in progress at site.
Sub-Project Main Components / Scope of work View Photo Gallery
Latest Photos
Guard_wall_stone_tile_work Guard_wall_stone_tile_work Seating_out_Red_stone_work Seating_out_Red_stone_work Rest_shed_kota_stone_work Rest_shed_kota_stone_work
Public Consultation / Disclosure / Orientation Meeting Total Employment (Skilled / Unskilled) Labor
No. of Community member involved
Male Female Total Male Female Total
36 9 45
Pollution Status
AIR
Parameter Base Data Present Data
PM10 82.7 82.3
SO2 18.2 18.5
NO2 14.1 14.2
CO ND ND
Base Data: 06-02-2016
Present Data: 14-11-2016
Base Data Report Present Data Report
WATER
Parameter Base Data Present Data
Colour <5 <5
Turbidity Nil Nil
pH 7.4 7.3
Total Hardness 169 174
TDS 378 381
MPN Not Detected Not Detected
Faecal Coliform Not Detected Not Detected
Base Data: 09-02-2016
Present Data: 14-11-2016
Base Data Report Present Data Report
NOISE
Parameter Base Data Present Data
Average 71.05 64.15
Maximum 72.3 65.5
Minimum 69.8 62.8
Leq. dB(A) 71.0 64.00
Base Data: 04-02-2016
Present Data: 14-11-2016
Base Data Report Present Data Report
News & Updates
  • ADB mission visiting IDIPT from August 27 to August 28, 2018.
  • 13th SLEC Meeting will be conducted on 05 July, 2018 at 05.00 pm under the Chairmanship of the Chief Secretary, Government of Uttarakhand at his Conference Hall.
  • Review Meeting held on  September 04th 2017 at UTDB Conference Hall. The Secretary & Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from May 23, 2017 till May 26, 2017. ADB Review meeting is going to be held on May 25,2017 at IDIPT conference hall.
  • UTTARAKHAND HIMMLAYAN MTB CHALLENGE  (3rd  Edition) of  8th - 16th April 2017 for participation ditails please visit website : www mtbuttarakhand.co.in
  • ADB mission visiting IDIPT from November 28, 2016 till December 02, 2016. ADB Review meeting is going to be held on December 01,2016 at IDIPT conference hall.
  • This is to inform you that Asan Conservation Resort,  Dehradun constructed under ADB Assistant Project is being inaugurated on 06 Aug 2016 by the Hon,ble tourism Minister, Govt of Uttarakhand
  • Review Meeting held on May 5 & 6 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • Review Meeting held on March 17 & 18 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from February 22 to February 25, 2016.
  • Work shop on environment and social safeguards 20th February 2016 IDIPT (UTDB)
  • Review Meeting held on February 9,10 & 11 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • Review Meeting held on January 23, 2018 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • ADB mission visiting IDIPT from March 27 to March 29, 2018.