Sub-Projects (Tranche - II & Tranche - III)

Package No.
PCSS
Status / Contract Type
Contractor Name SLEC Approved DPR Cost (INR Crore) Contract Amount
(US $ Million)
($1=63.00 INR)
ADB Financing
(US $ Million)
($1=63.00 INR)
Agreement Date
UK/IDIPT/DDN/06 - Lot 2 P-2
0053
Awarded / Works
M/s Samir Kumar Mishra Badaripur, Dehradun
Badaripur, Dehradun Uttarakhand

0.58

0.09

(INR 5.76 Million)
(INR 0.58 Crore)
With Variation
0.14
(INR 8.98 Million)
(INR 0.90 Crore)
0.05
59% of Award Value
30-05-2016
Contract Start Date Contract Period Completion Date
(As per contract start date)
Sub-Project Valley
30-05-2016 18 Months 29-11-2017 29-11-2017 Mandakini,Alaknanda & Bhagirathi Valley
Sub-Project Output
Overall Physical Progress(%) as on November 2017 & Financial Progress (%) till date
Physical Progress (%) Financial Progress (%) Disbursed
(INR Million)
Remarks
95.00 58.42 5.25 Final finishing work is in progress


1st Ra Bill Rs.12,46,527.38
2nd Ra Bill Rs15,42,359.81
3rd Ra Bill :-Rs.12,97,497.42
4th Ra Bill :-Rs. 15,84,954.86
with Gross Amount Rs.56,71,339.47
Contract amount Rs. 57,57,777.59
VARIATION DETAIL :-
1st Variation Rs14,28,298.02 Lacs
2nd Variation Rs 17,96,001.39
Revised Contract Amount Rs.89,82,046.97 Lacs
Sub-Project Main Components / Scope of work View Photo Gallery
  • Construction of Compound Wall
Latest Photos
Interpretation center at Tanakpur Interpretation center at Tanakpur Paver block at interpretation centre Tanakpur Paver block at interpretation centre Tanakpur Interpretation centre at Tanakpur Interpretation centre at Tanakpur
Public Consultation / Disclosure / Orientation Meeting Total Employment (Skilled / Unskilled) Labor
No. of Community member involved
Male Female Total Male Female Total
390 57 447
Pollution Status
AIR
Parameter Base Data Present Data
PM10
SO2
NO2
CO
WATER
Parameter Base Data Present Data
Colour
Turbidity
pH
Total Hardness
TDS
MPN
Faecal Coliform
NOISE
Parameter Base Data Present Data
Average
Maximum
Minimum
Leq. dB(A)
News & Updates
  • Review Meeting held on  September 04th 2017 at UTDB Conference Hall. The Secretary & Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from May 23, 2017 till May 26, 2017. ADB Review meeting is going to be held on May 25,2017 at IDIPT conference hall.
  • UTTARAKHAND HIMMLAYAN MTB CHALLENGE  (3rd  Edition) of  8th - 16th April 2017 for participation ditails please visit website : www mtbuttarakhand.co.in
  • ADB mission visiting IDIPT from November 28, 2016 till December 02, 2016. ADB Review meeting is going to be held on December 01,2016 at IDIPT conference hall.
  • This is to inform you that Asan Conservation Resort,  Dehradun constructed under ADB Assistant Project is being inaugurated on 06 Aug 2016 by the Hon,ble tourism Minister, Govt of Uttarakhand
  • Review Meeting held on May 5 & 6 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • Review Meeting held on March 17 & 18 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from February 22 to February 25, 2016.
  • Work shop on environment and social safeguards 20th February 2016 IDIPT (UTDB)
  • Review Meeting held on February 9,10 & 11 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • ADB & DEA has approved the Tranche - III and loan signing is fixed on September 28, 2015 in GoI, MoF, New Delhi.

  • ADB mission visiting IDIPT from September 21 to September 30, 2015.

    The objective is to observe the performance of ongoing sub-projects.

  • CTS Review Meeting held on September 14, 2015 at UTDB Conference Hall. Addl. Program Director, IDIPT chaired the meeting.

    The objective of the meeting was to discuss progress reports, identify new tourist destinations etc.

  • Review Meeting held on August 10, 2015 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.

    The objective of the meeting was to discuss the physical & financial progress of ongoing sub-projects of Tranche - II