Sub-Projects (Tranche - II & Tranche - III)

Package No.
PCSS
Status / Contract Type
Contractor Name SLEC Approved DPR Cost (INR Crore) Contract Amount
(US $ Million)
($1=63.00 INR)
ADB Financing
(US $ Million)
($1=63.00 INR)
Agreement Date
UK/IDIPT/BHT/01
0012
Awarded / Works
M/s Dagmo Riba
Ground Floor, A-3, 49-50, Sector-11, Rohini Delhi - 110085

4.62

0.70

(INR 43.91 Million)
(INR 4.39 Crore)
With Variation
0.80
(INR 50.57 Million)
(INR 5.06 Crore)
0.41
59% of Award Value
15-05-2014
Contract Start Date Contract Period Completion Date
(As per contract start date)
Sub-Project Valley
17-07-2014 18 Months
Ext. 18.46(M)
14-11-2015
29-06-2017
16-01-2016
31-08-2017
Gola River Valley
Sub-Project Output
  • Urban infrastructure and services at tourist destinations and attractions
Overall Physical Progress(%) as on September 2017 & Financial Progress (%) till date
Physical Progress (%) Financial Progress (%) Disbursed
(INR Million)
Remarks
80.32 43.11 21.80 A- Restaurant Building (92%)
a- Masnory chamber making work is under progress.
b- Railing painting work is under progress.
B- Main Building (60%)
a- External pointing work is under progress.
b- Building stone wall repairing has been completed.
c- Cleaning of Stone surface is under progress.
d- False Ceiling work is under progress.
e- Repairing and Fixing of wooden purlins (for roofing) are under progress.
f- Repairing and refixing of wooden beams are under progress.
g- Fixing of GI sheet is under progress.
h- Lean concrete under flooring is under progress.
i- Anti Termite Treatment (A. T. T.) work under flooring is under progress.
j- Fixing of GI Ridge & Hips work are under progress.
k- Cement plaster work is under progress.
l- Wooden window panelled and glazed shutter making work are 80% completed.
m- Toilet brick work is completed.
n- Wooden flooring work is completed.
o- Cement concrete gola 1:2:4 work is under progress.
C-L. A. Work (80%)
a- Pathway gravel laying work is under progress.
b- Local Patal work over Amphitheater steps is under progress.
c- Cafe deck gravel laying in floor work is under progress.
d- Surface prepration work is under progress for land-scaping.
e- Doob grass work is under progress.
f- Kota Stone fixing in stair work is under progress.
g- Cafe deck CC flooring work is under progress.
h- Main parking area PCC work is under progress.
i- Railing making work/painting work is under progress.
D-Annexe Building (78%)
a-Toilet wall & floor tile fixing work are under progress.
b- Door & window fixture fixing work are under progess.
c- Rough cast plaster outer face work is under progress.
d- Wire gauze shutter door & window polishing works are under progress.
e-Gutter paiting work is under progress.
f-Main hole making work is under progress.
g-Electrical earthing work is under progress.
E- Dormitory Building (95%)
a- Toilet floor & wall tile fixing work are under progress.
b- UPVC door frame & panel fixing work is completed.
c- Roof painting work is completed.
d- Expose stone masnory varnish coating work is under progress.
e- Toilet fixture fitting work is under progress.
f- Sanitary fixture fitting work is under progress.
g-Rain water down pipe fixing work is under progress.
h-Main hole chamber making work is under progress.
i-Electrical panel fixing work is under progress.
F-Services (55%)
a-External water supply line work is under progress.
b-Underground water tank tile fixing work is under progress.
c-Monolicth pump fixing work is under progress.
d-Main hole sewer line laying is under progress.
e-Septic tank covering work is under progress.
G-Rehabilitation of Tent Platform (98.73%)
a- All tent platform work is completed.
Sub-Project Main Components / Scope of work View Photo Gallery
Latest Photos
Windows polishing work at Annex building Windows polishing work at Annex building main Building ground floor tiling work main Building ground floor tiling work False ceiling finishing work at main Building False ceiling finishing work at main Building
Public Consultation / Disclosure / Orientation Meeting Total Employment (Skilled / Unskilled) Labor
No. of Community member involved
Male Female Total Male Female Total
23 5 28
Pollution Status
AIR
Parameter Base Data Present Data
PM10 54-64 60.10
SO2 06-10 7.30
NO2 14-18 18.10
CO - 0.40
Base Data: 09-07-2013
Present Data: 15-03-2016
Base Data Report Present Data Report
WATER
Parameter Base Data Present Data
Colour < 5 < 5
Turbidity < 1 BDL
pH 7.8 7.25
Total Hardness 58 68
TDS 280.9 206
MPN 175 < 2/100 ml
Faecal Coliform 15 Absent
Base Data: 18-05-2013
Present Data: 15-03-2016
Base Data Report Present Data Report
NOISE
Parameter Base Data Present Data
Average 50 dB(A) 46.25 dB(A)
Maximum 40.8 dB(A) 56.3 dB(A)
Minimum 39.4 dB(A) 36.2 dB(A)
Leq. dB(A) 55 dB(A) 65.0 dB(A)
Base Data: 09-07-2013
Present Data: 15-03-2016
Base Data Report Present Data Report
News & Updates
  • Review Meeting held on  September 04th 2017 at UTDB Conference Hall. The Secretary & Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from May 23, 2017 till May 26, 2017. ADB Review meeting is going to be held on May 25,2017 at IDIPT conference hall.
  • UTTARAKHAND HIMMLAYAN MTB CHALLENGE  (3rd  Edition) of  8th - 16th April 2017 for participation ditails please visit website : www mtbuttarakhand.co.in
  • ADB mission visiting IDIPT from November 28, 2016 till December 02, 2016. ADB Review meeting is going to be held on December 01,2016 at IDIPT conference hall.
  • This is to inform you that Asan Conservation Resort,  Dehradun constructed under ADB Assistant Project is being inaugurated on 06 Aug 2016 by the Hon,ble tourism Minister, Govt of Uttarakhand
  • Review Meeting held on May 5 & 6 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • Review Meeting held on March 17 & 18 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from February 22 to February 25, 2016.
  • Work shop on environment and social safeguards 20th February 2016 IDIPT (UTDB)
  • Review Meeting held on February 9,10 & 11 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • ADB & DEA has approved the Tranche - III and loan signing is fixed on September 28, 2015 in GoI, MoF, New Delhi.

  • ADB mission visiting IDIPT from September 21 to September 30, 2015.

    The objective is to observe the performance of ongoing sub-projects.

  • CTS Review Meeting held on September 14, 2015 at UTDB Conference Hall. Addl. Program Director, IDIPT chaired the meeting.

    The objective of the meeting was to discuss progress reports, identify new tourist destinations etc.

  • Review Meeting held on August 10, 2015 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.

    The objective of the meeting was to discuss the physical & financial progress of ongoing sub-projects of Tranche - II