Sub-Projects (Tranche - II & Tranche - III)

Package No.
PCSS
Status / Contract Type
Contractor Name SLEC Approved DPR Cost (INR Crore) Contract Amount
(US $ Million)
($1=63.00 INR)
ADB Financing
(US $ Million)
($1=63.00 INR)
Agreement Date
UK/IDIPT/BHT/01
0012
Awarded / Works
M/s Dagmo Riba
Ground Floor, A-3, 49-50, Sector-11, Rohini Delhi - 110085

4.62

0.70

(INR 43.91 Million)
(INR 4.39 Crore)
With Variation
0.80
(INR 50.30 Million)
(INR 5.03 Crore)
0.41
59% of Award Value
15-05-2014
Contract Start Date Contract Period Completion Date
(As per contract start date)
Sub-Project Valley
17-07-2014 18 Months
Ext. 18.46(M)
14-11-2015
29-06-2017
16-01-2016
31-08-2017
Gola River Valley
Sub-Project Output
  • Urban infrastructure and services at tourist destinations and attractions
Overall Physical Progress(%) as on January 2018 & Financial Progress (%) till date
Physical Progress (%) Financial Progress (%) Disbursed
(INR Million)
Remarks
100.00 65.58 32.98 A- Restaurant Building (100%)
a- False ceiling work is in both the ground floor and first floor are completed.
b- Fixing of window frame is completed.
c- UPVC door frame & panel fixing work is completed.
d- Electrical work (wireing, point, G. I. box, modular etc. work) is completed.
e- Expose stone masnory varnish coating work is completed.
f- Finishing (Painting, Putty etc.) works are completed.
g- Sink fitting works is completed.
h-Toughened glass work is completed.
i- Masnory chamber making work is completed.
j- Railing painting work is completed.
k- Customize furniture fitting work is completed.
B- Main Building (100%)
a- External pointing work is completed.
b- Building stone wall repairing has been completed.
c- Cleaning of Stone surface is completed.
d- False Ceiling work is completed.
e- Repairing and Fixing of wooden purlins (for roofing) are completed.
f- Repairing and refixing of wooden beams are completed.
g- Fixing of GI sheet is completed.
h- Lean concrete under flooring is completed.
i- Anti Termite Treatment (A. T. T.) work under flooring is completed.
j- Fixing of GI Ridge & Hips work are completed.
k- Cement plaster work is completed.
l- Wooden window panelled and glazed shutter making work are completed.
m- Toilet brick work is completed.
n- Wooden flooring work is completed.
o- Cement concrete gola 1:2:4 work is completed.
p- Wooden railing work is completed.
q- Toilet under ground water and sanitary fitting work is completed.
r- Room floor & toilet wall tiling works are completed.
s- Mailamine polishing work is completed.
t- Preparation of water proffing chemical work is completed.
u- Decorative false ceiling polishing works are completed.
v-Electrical wiring work is completed.
w-Mud motar Poiting repairing work is completed.
x-Window Glass fixing work is completed.
y- Sanitary item main building (hindware) fixing work is completed.
z- Main building old window repairing and glass fixing work is completed.
aa- Main building electrical panel fixing work is completed.
C-L. A. Work (100%)
a- Pathway gravel laying work is completed.
b- Local Patal work over Amphitheater steps is completed.
c- Cafe deck gravel laying in floor work is completed.
d- Surface prepration work is completed for land-scaping.
e- Doob grass work is completed.
f- Kota Stone fixing in stair work is completed.
g- Cafe deck CC flooring work is completed.
h- Main parking area PCC work is completed.
i- Railing making work/painting work is completed.
D-Annexe Building (100%)
a-Toilet wall & floor tile fixing work are completed.
b- Door & window fixture fixing work are completed.
c- Rough cast plaster outer face work is completed.
d- Wire gauze shutter door & window polishing works are completed.
e- Gutter paiting work is completed.
f- Main hole making work is completed.
g- Electrical earthing work is completed.
h- Godrej furniture fitting work is completed.
E- Dormitory Building (100%)
a- Expose stone masnory varnish coating work is completed.
b- Toilet fixture fitting work is completed.
c- Sanitary fixture fitting work is completed.
d-Rain water down pipe fixing work is completed.
e-Main hole chamber making work is completed.
f-Electrical panel fixing work is completed.
g- Customize furniture fitting work is completed.
F-Services (100%)
a-External water supply line work is completed.
b-Underground water tank tile fixing work is under progress.
c-Monolicth pump fixing work is completed.
d-Main hole sewer line laying is completed.
e-Septic tank covering work is completed.
G-Rehabilitation of Tent Platform (100%)
a- All tent platform work is completed.
Sub-Project Main Components / Scope of work View Photo Gallery
Latest Photos
View of Annese Building View of Annese Building Septic tank Septic tank Side View of Annexe builidng Side View of Annexe builidng
Public Consultation / Disclosure / Orientation Meeting Total Employment (Skilled / Unskilled) Labor
No. of Community member involved
Male Female Total Male Female Total
8 8
Pollution Status
AIR
Parameter Base Data Present Data
PM10 54-64 60.10
SO2 06-10 7.30
NO2 14-18 18.10
CO - 0.40
Base Data: 09-07-2013
Present Data: 15-03-2016
Base Data Report Present Data Report
WATER
Parameter Base Data Present Data
Colour < 5 < 5
Turbidity < 1 BDL
pH 7.8 7.25
Total Hardness 58 68
TDS 280.9 206
MPN 175 < 2/100 ml
Faecal Coliform 15 Absent
Base Data: 18-05-2013
Present Data: 15-03-2016
Base Data Report Present Data Report
NOISE
Parameter Base Data Present Data
Average 50 dB(A) 46.25 dB(A)
Maximum 40.8 dB(A) 56.3 dB(A)
Minimum 39.4 dB(A) 36.2 dB(A)
Leq. dB(A) 55 dB(A) 65.0 dB(A)
Base Data: 09-07-2013
Present Data: 15-03-2016
Base Data Report Present Data Report
News & Updates
  • Review Meeting held on  September 04th 2017 at UTDB Conference Hall. The Secretary & Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from May 23, 2017 till May 26, 2017. ADB Review meeting is going to be held on May 25,2017 at IDIPT conference hall.
  • UTTARAKHAND HIMMLAYAN MTB CHALLENGE  (3rd  Edition) of  8th - 16th April 2017 for participation ditails please visit website : www mtbuttarakhand.co.in
  • ADB mission visiting IDIPT from November 28, 2016 till December 02, 2016. ADB Review meeting is going to be held on December 01,2016 at IDIPT conference hall.
  • This is to inform you that Asan Conservation Resort,  Dehradun constructed under ADB Assistant Project is being inaugurated on 06 Aug 2016 by the Hon,ble tourism Minister, Govt of Uttarakhand
  • Review Meeting held on May 5 & 6 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • Review Meeting held on March 17 & 18 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting
  • ADB mission visiting IDIPT from February 22 to February 25, 2016.
  • Work shop on environment and social safeguards 20th February 2016 IDIPT (UTDB)
  • Review Meeting held on February 9,10 & 11 2016 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.
  • ADB & DEA has approved the Tranche - III and loan signing is fixed on September 28, 2015 in GoI, MoF, New Delhi.

  • ADB mission visiting IDIPT from September 21 to September 30, 2015.

    The objective is to observe the performance of ongoing sub-projects.

  • CTS Review Meeting held on September 14, 2015 at UTDB Conference Hall. Addl. Program Director, IDIPT chaired the meeting.

    The objective of the meeting was to discuss progress reports, identify new tourist destinations etc.

  • Review Meeting held on August 10, 2015 at UTDB Conference Hall. The Program Director, IDIPT chaired the meeting.

    The objective of the meeting was to discuss the physical & financial progress of ongoing sub-projects of Tranche - II

Other Links